Budget comparison by item (Budget console)
Check the comparison between the budget and the actual data registered based on the templates of the balance sheet, profit and loss statement, sales/management expenses report and cost report.
→To Operation Procedure
Screen Transition
[Basic Console Module]
↓
[Budget Console]
↓
[Budget Comparison by Item] or [Budget Comparison by Item 2] (B/S)/(P/L)/(Sales/Management Expenses)/(Cost Report)
↓
[Budget comparison by item] screen
Objects setup
[Searching Condition]
- Term
Specify the term for budget comparison by item.
- Template
Set the template code specified by the accounting department.
- Item
Select an item for comparison from [Department], [Correspondent], [Project Code 1], [Project Code 2], [Accounting Analysis Code 1], [Accounting Analysis Code 2] and [D Description].
Normally, select [Department] and enter the actual department or summary department.
- Budget Code
Enter the budget code specified by the accounting department.
- Row No.
The total number of rows in the spread is displayed.
-
Include Unapproved
To include unapproved budget in the budget comparison, check the box.
[Data Level]
-
1 - 20
Check the data level for budget comparison.
[Select Row]
- Summary Amount
Select between [All], [Achievement Rate] and [Difference]. When [Achievement Rate] or [Difference] is selected, enter the achievement rate or difference.
- Summary Period
Select between [PS Term Amt] and [Total Amt].
- Summary Unit
Select the summary unit to display the amount between [Summary A/C 1], [Summary A/C 2], [Summary A/C 3] and [A/C // Sub A/C].
- Row to Display
Specify the row number of the spread to select the specified row.
[Spread]
- ,
Clicking drills down the data to the details of [Summary A/C 1], [Summary A/C 2], [Summary A/C 3] and [A/C] for reference. The changes into when the data has been drilled down.
- Summary A/C 1 - 3
If [Summary A/C 1], [Summary A/C 2] or [Summary A/C 3] has been selected in [Summary Unit], the names of the summary A/C registered with the
[Financial
Statement module] are displayed.
- A/C Code, Sub A/C
If [A/C // Sub A/C] has been selected in [Summary Unit], the A/C name and sub A/C name are displayed.
- Budget Amt, Actual Amt
Shows the budget and actual amounts summarized based on the [Select Row] setting.
-
Difference
Shows the difference between the budget and actual amounts.
-
Achievement Rate
Shows the achievement rate of the actual amount to budget.
[Print]
-
Output All
All budget comparisons shown in the spread are output to Excel or printed.
[Buttons]
- (Refer Term Balance update)
Shows in a separate window the condition of balance update for the term specified in [Term].
-
Refer
- (Tracking)
Shows the data below the level displayed by drilldown with and in the [Tracking Console 3] screen.
- Excel output
Excel is started and a list is displayed containing only the budget comparisons selected in the spread. If the [Output All] box is checked, all of the budget comparisons in the spread are displayed in an Excel file. The data can be saved/ printed with Excel.
- Print
A list is displayed in the Print Preview window containing only the budget comparisons selected in the spread. If the [Output All] box is checked, all of the budget comparisons in the spread are displayed in an Excel file. The data can be printed with the Print Preview window.
- (Graphics)
The rows selected in the spread are retrieved for graphical display of the budget comparison.
- (Column Searching)
The [Column Searching] screen is displayed to allow column searching of the spared.
- Display Name 1 (Name1/2)
-
Clear
-
Exit